Daily Work Schedule
Click here to sign up
Monday, July 13, 9 am to 9 pm
Tear out carpet
Take out ceiling tile
Remove kitchen cabinets
Install ceiling fans
Install new ceiling tile
Caulk ceiling tile
Clean and repair walls
Clean woodwork
Install wall outlets
Install wheel chair ramp
Install outdoor lighting
Tuesday, July 14, 9 am to 9 pm
Paint walls
Paint woodwork
Take off doors and paint
Repair doors
Tile kitchen (after woodwork, before cabinet, 4-6 hours, 2-3 people)
Tile bathroom floor (take out toilet and vanity)
Install new vanity
Landscaping
Repair banister to second floor
Wednesday, July 15, 9 am to 9 pm
Finish kitchen floor
Install kitchen cabinet
Clean kitchen appliances
Finish bathroom
Touch up paint
Install carpet
Pick up furniture (loaded on truck)
Finish landscaping
Thursday, July 16, 9 am to 9 pm
Finish everything
Move in furniture
Hang curtains
Hang pictures
Party at 7 PM
Set up party
Clean up party
Supplies needed
Windex
Paper towels
Painting supplies (brushes, rollers, drop clothes, roller pans)
Cleaning supplies (buckets, rags, cleaners, etc.)
Still need…
Ceiling fans
Twin beds
Dressers
Wall to Wall Carpet – 100 yds squared
General
Bring your tools. Please label them.
Click here to sign up to volunteer.